Ready-mix concrete supplied in largest ever city centre office project outside of London over winter
We supplied nearly 6,000m3 of WeatherMix® concrete for the ongoing redevelopment of Snow Hill station – a 420,000 sq ft regeneration project to transform Birmingham’s main business district
The Background
As part of ambitious plans to revamp the major transport hub at the heart of the UK’s second city, new office buildings will replace the station’s multi-storey car park in order to create what’s been dubbed as ‘Birmingham’s Canary Wharf’.
Once complete, the Snow Hill refurbishment will reshape Birmingham’s skyline and transform the front of St Chad’s Queensway - one of the most prominent gateways to the city centre.
The Problem
Aggregate Industries was awarded the contract to supply ready-mixed concrete to the largest ever city centre office scheme built outside London by Thames Formwork under main contractor, BAM Construction.
As one of the biggest slipform constructions outside the capital, a key challenge of the £90 million project was that work had to be completed during the colder winter months.
The Solution
The natural choice was to use Aggregate Industries WeatherMix, a concrete solution specifically designed to tolerate colder conditions than standard mixes.
Approximately, 6,000m3 of WeatherMix as well as standard concrete and 11,000m3 Strike® - one of Aggregate Industries high early strength concrete mixes – were supplied to the project throughout the 2017 winter period.
By accelerating the setting time, which provides early protection against freezing, WeatherMix allows the placement of concrete across a range of ambient temperatures down to zero, ensuring contractors are able to meet tight timescales, whilst assuring the quality of the concrete
The revolutionary WeatherMix product, together with Strike, enabled the contractor on the site to extend the construction season and work throughout January and February, during which Birmingham experienced 24 working days where temperatures fell below 4°C degrees.
As a result, WeatherMix allowed Thames Formwork to continue to construct with confidence during this period, playing a vital role in the project’s success.
Daniel King, Aggregate Industries General Manager for the Midlands & North, said: “The ambitious regeneration of the Snow Hill site will create what has been coined as ‘Birmingham’s Canary Wharf’, providing much needed office space in the heart of the city.
“It is the latest in a series of projects we are working on to provide concrete for the city’s construction boom, set to transform Birmingham’s skyline. With our innovative WeatherMix solution, we were able to support the contractor to meet their tight deadline by keeping the concrete supply and the project on schedule.”
Wayne Rock, Construction Director at Thames Formwork, comments: “With a project as difficult and complex as this, it was very important for us to work with a concrete supplier that could help us work through the winter months and stay on track for completion.
With excellent workability, and pumpability characteristics, WeatherMix is ideal for projects with complex formwork. Available in high-early strengths, the product provides advanced finishing characteristics for flatwork and cast systems, where finishing times are comparable to concrete placed in ambient temperatures.
The Snow Hill project is the latest in a series of contracts Aggregate Industries’ has secured to supply concrete to Birmingham’s city centre regeneration.
Most recently, working with contractor MPB Structures, Aggregate Industries supplied a combined 28,000m of ready-mixed concrete for the Arena Tower residential development and Arena Central – the new landmark headquarters of UK banking giant HSBC.
- Millbrook Road West resurfaced with low carbon SuperLow asphalt
- Aggregate Industries supports in creating the UK’s first ‘clean air’ substation
- Aggregate Industries offers green solution to A46 Warwick Bypass project
- Aggregate Industries lightens the load for Transport for London
- Aggregate Industries carries the load on ‘first of its kind’ Nene Bridge repair - Case Study
Project details
-
Sector
High rise
-
Client
Thames Formwork
-
Contractor
BAM Construction
-
Other information
- Supplied nearly 6,000m3 of WeatherMix® concrete
- Specifically designed to tolerate colder conditions
“The team at Aggregate Industries didn’t disappoint, and without their customised WeatherMix solutions and just-in-time deliveries, we would’ve had to stop work on the project during the colder temperature months, putting the timescales of the project in jeopardy. We were genuinely impressed with the seamless service you’d expect from a market leader; we look forward to working with the business again in the future.”
WeatherMix has been specially developed to support and extend the construction season into the winter months.