Aggregate Industries Overseas was able to supply high quality and large volumnes of aggregate required for the successful construciton of the channel tunnel.

26.01.2012
 

Solution

The supply terminal at the Isle of Grain, Kent was established to supply this project. This dedicated site offered sufficient land to enable TML to construct their segment production factories and storage yard infrastructure from which the segments were transported by rail direct to the tunnel head.

All other aggregate products required at the tunnel head site and the rail ballast were also transported by train from the Isle of Grain import terminal to two on-site rail distribution depots which were operationally managed from the Isle of Grain terminal as a total logistics package.

Glensanda granite was chosen as the preferred concreting aggregate due to its non reactive and low heat generation properties due to the high cement content of the high strength concrete.

We continued to do more work on the  Channel Tunnel Rail Link.

Project details

  • Civil engineering

  • Eurotunnel 

  • TML (TransManche Link)

  • Over a project duration of 6 years
    1.2 million tonnes of concreting sand and aggregates for the production of tunnel segments
    1.1 million tonnes of concreting sand, concreting aggregates and other crushed granite products for construction work direct at the tunnel head
    1.0 million tonnes of rail ballast for the rail link and train marshalling yards.